Skip Global Navigation and Quick Links or Go to Global Navigation or Go to Quick Links
Transportation & Engineering
100 Jefferson County Pkwy, Ste. 3500
Golden, CO 80419
303-271-8495

by  
Go to H & T Navigation


 

Welcome to Jefferson County Transportation & Engineering Department.

Design Projects


Golden Gate Road Improvements (Grange)
Deer Creek Canyon Road Shoulder Widening
6th Avenue Frontage Road Trail Project
North Coon Creek at Miller Street Culvert Replacement
Wadsworth/Waterton Intersection
  
Quincy/Kipling Intersection 



Golden Gate Roadway Improvements (Grange)
Click here for enlarged image

Project Scope:  Within Golden Gate Canyon Road the County identified several areas for improvement last year based on safety of the traveling public, lack of raodway shoulders, and lack of clear zone for existing structures.  The curve adjacent to the Grange was identified as an area needing improvements.

The existing curve is a tight s-curve with five access points.  The County is proposing to reduce the access points from five to three.  In addition the County will be increasing the existing curve radius from 75 feet to 150 feet.  Increasing the radius of the curve will require the County to move the road to the southwest toward the creek.  Also there is an exisitng rock culvert with inadequate headwalls that are located within the safe clear zone.  Since the existing headwalls are made of rock, proper guardrail attachments are not possible.  The County is proposing to provide a new culvert vault that will connect the three culverts and remove the existing hazard of the headwall and the steep drop off that exists behind the headwall.

This project is being designed by Jefferson County staff.  Construction is anticipated to cost $200,000 and will be funded through traffic impact fees collected for Golden Gate Canyon Road.

Progress Update:  Public meeting for the Golden Gate projects was held on March 24, 2010.  Design plans are 50% complete.

Project Schedule:
Design                        Start:  November 2009                    End:  Fall 2010
Construction                Start:  Spring 2011                         End:  Summer 2011

Project Manager:  Contact Brent Soderlin with Jefferson County at (303) 271-8462 or bsoderli@jeffco.us if you have questions or concerns.

Back to Top


Deer Creek Canyon Road Shoulder WideningClick here for larger image

Project Scope:  This project is a continuation of the Deer Creek Canyon Road shoulder widening project of 2008.  Three areas of Deer Creek Canyon Road are targeted for shoulder widening.  The western most part is a 400 foot section in the Phillipsburg area; the central portion is an 1800 foot section between Phillipsburg and Grizzly Drive; the eastern portion is a 1500 section west of south Owens Street.  These sections of Deer Creek Canyon Road are narrow, where shoulders are virtually non-existent.  Safety will be greatly enhanced in these areas by adding a four-foot wide shoulder to the north side and a section of guardrail on the south side where Deer Creek converges with the roadway.

The project is being funded by Jefferson County and is anticipated to cost approximately $400,000.

Project Update:  Design plans are 100 percent complete.

Project Progress:  Finalizing access permit/license agreement with Xcel Energy.

Project Schedule:  
Design                            Start:  March2010                     End:  Complete
Construction                    Start:  October 2010                 End:   April 2011

Project Manager:  Contact John Conn with Jefferson County at 303.271.8496 or jconn@jeffco.us if you have questions or concerns.

Back to Top


6th Avenue Frontage Road Trail Project

Click here to enlarge image
Project Scope:  This project consists of constructing curb, gutter and an 8-foot wide sidewalk along the south side of the frontage road between Deframe Court and Gladiola Street in Golden, CO.  The design also includes updating existing storm sewer inlets and constructing handicap access ramps in the medians at Deframe Court, Flora Way, and Gladiola Street.  The project is approximately 2,000 feet in length.

The project is being designed by Jefferson County staff.  Construction will be funded by Jefferson County.

Progress Update:  Preliminary design is underway.

Public Open House: 
When: 
August 17th 6-8:00 PM
Where:  Jeffco Fairgrounds Exhibit Hall 3
What:  Sidewalk construction from Gladiola to Deframe on the south side of 6th Avenue Frontage Road

Project Schedule:
Design                            Start:  April 2010                        End:  August 2010
Construction                    Start:  2011                                End:  2011

Project Manager:  Contact Alecia Cope with Jefferson County at 303.271.8456 or acope@jeffco.us if you have questions or concerns.

Back to Top


North Coon Creek at Miller Street Culvert Replacement North Coon Creek Culvert

Project Scope:  This project will result in the removal of an existing 36 inch diameter culvert crossing South Miller Street and replacing it with a 4 foot by 12 foot concrete box culvert.  This project requirement was identified during the 2008 Dutch Creek, Coon Creek, Lilley Gulch and Three Lakes Tributary Major Drainageway Planning & Flood Hazard Area Delineation Study.  The existing culvert is totally inadequate to accommodte the major rainfall events.  If the existing culvert were left in place it could result in the flooding of a nearby home and the overtopping of Miller Street with flood waters.  Should Miller Street breach, the downstream flooding could be catastrophic to residences and an assisted care living center.

The project costs are being shared by Jefferson County and Urban Drainage and Flood Control District.  The project is anticipated to cost approximately $350,000.

Project Update:  ICON Engineering is the design engineer and construction plans are approximately 70 percent complete.

Project Schdedule:
Design                        Start:  August 2009                     End:  Sept. 2010
Construction                Start:  October 2010                   End:  Feb. 2011
 

Project Manager:  Contact John Conn with Jefferson County at 303.271.8496 or jconn@jeffco.us if you have questions or concerns.

Back to Top

 


Wadsworth/Waterton Intersection

Project Scope:  The project will initially study the universe of alternatives for improving the safety and capacity of the intersection as well as evaluating the environmental impacts (i.e. the Feasibility Study).  Preliminary and final engineering design plans will be done for the Locally Preferred Alternative (i.e. the Recommended Alternative).  The design will be done in a manner that is sensitive to the existing environment and to the adjacent  

Wads Waterton and Quincy 

property owners' concerns (i.e. Context Sensitive Design).  Numerous public meetings will be held to assess the community's concerns and comments on each alternative which will be key to the decision making process.

The project is a cooperative effort by Jefferson County, Douglas County, and Lockheed Martin.  Funding for the initial alternative analysis and the preliminary design phase is being shared equally between the three stakeholders.  Other key agencies on the project are CDOT, the US Army Corps of Engineers, the National Audubon Society, Denver Water, and Colorado State Parks.  Jefferson County's share of the funding is from the County's Impact Fee Fund.  The engineering consulting services are being done by Jacobs Engineering.

 

 

 

 

 


  

 

 

 


 

Project Update:  View Feasibility Study
 
 

Project Schedule:    
Feasibility Study Alternatives Start: October 2008 End: July 2009
Preliminary Design Start: July 2009  End: August 2010
Environmental Clearance Start: January 2009 End: September 2010 
Final Design  Start: August 2010 End: January 2011 
Right-of-Way Acquisition Not Yet Scheduled  
Construction  Not Yet Scheduled  

  

 

 


 

Project Manager:  Contact Brad Bauer with Jefferson County at 303-271-8495 or bbauer@jeffco.us if you have questions or concerns. 

 

 
 
Back to Top



Quincy/Kipling Intersection

Project Scope:  The project plans will provide for four through lanes on West QuincyQuincy & Kipling Intersection Avenue through the South Kipling Parkway intersection.  The project will provide for new acceleration and deceleration lanes as well as double left-turn lanes for West Quincy Avenue.  Drainage improvements as well as sidewalks will also be included in the design.  Improvements at the Quincy/Kipling intersection will generally be made in accordance with the safety and capacity enhancements that were proposed in the County's plans for the intersection in the 2006 Quincy Corridor Study.  The project is funded with a federal grant ($1.2 million) and by the County's Impact Fee Fund.  The design is being done by Muller Engineering. 

 

 

 

 

 

 

 

  

Progress Update:
A public meeting was held December 9, 2008, for the preliminary design.  The final design of the intersection improvements is completed, and Xcel Energy is ordering the materials for the relocation of three 115 KV electric transmission line poles. 
View Meeting Presentation
View Meeting Minutes
 


 

 


 

Project Schedule:     
Design Start: January 2008 End: April 2009
Right-of-Way Acquisition Start: July 2009 End: August 2010
Construction Start: March 2011 End: December 2011

  

 


Project Manager:
Contact Brad Bauer with Jefferson County at 300-271-8495 or bbauer@jeffco.us if you have questions or concerns.
  

 

Back to Top  

 

 

 

Last Modified: Sep 1, 2010 11:37 AM

Copyright © 2006-2009 - Jefferson County, Colorado. All rights reserved.
Login
Home