by Public Information
comments open from April 18 until May 7
While the driest March on record kept our foliage thirsting for water, it certainly benefited crews working on the West Rail Line. Construction activities geared up earlier than expected and the summer-like temperatures led to uninterrupted work flow.
First Light Rail car passes through West Rail Line
RTD began initial clearance testing on the line on March 22 as crews used a unimog (similar to a rail tugboat) to pull a light rail vehicle along the whole alignment. The pull took one and a half days to traverse the entire line and back; beginning just south of the newly relocated Auraria West Station in downtown Denver and ending at the Jefferson County Government Center before turning around and heading back downtown.
This initial test confirmed clearances between the vehicle and surrounding elements of the rail line including; bridges, tunnels, soundwalls, fencing, poles and station platforms along the alignment. RTD will continue intermittent tests along the West Rail Line until it opens in May of 2013.
Sheridan parking structure
Design of the 800-space parking structure at 10th Avenue and Sheridan Boulevard is approximately 60 percent complete, with a target construction start date in June 2012. Swinerton Builders anticipates grading will occur on the site for approximately two weeks, followed by foundation work slated to start in mid-June. The structure will be cast-in-place concrete and use aluminum storefront framing and glass to create a contemporary architectural look.
Pedestrian safety recommendations
A light rail pedestrian accident in Utah spurred heightened awareness for light rail crossing safety across the nation. The Federal Transit Administration has asked transit agencies, including RTD, to review all at-grade crossings and make recommendations for pedestrian safety enhancements.
A committee, made up of members from many RTD departments, was created and a series of recommended changes were developed. Multiple West Rail Line grade crossings have potential changes based on this recent safety review. Changes to any grade crossing will require the approval of the PUC (Public Utilities Commission) prior to being implemented. Following are the recommended changes:
• Fencing will be extended between the soundwalls and signal masts at Pierce, Teller, Carr, Garrison, Independence, and Oak.
• Bollards will be placed between the soundwall and signal masts at Pierce, Teller, Carr, and Estes.
• Either the signal mast will be moved behind the sidewalk or a swing gate will be placed between the signal and soundwall at Carr.
• Swing gates between the signal and soundwall will be placed at Estes, Independence, and Oak.
• Track panels that currently extend past the preferred walkway will be removed at Garrison and Independence.
• 100 feet of soundwall will be removed on the southwest corner at Independence as well as a 24/7 speed restriction of 20 mph at that same intersection.
• Lastly, “No trespassing” signs will be placed at each corner of all grade crossings.
Once these recommendations are approved by the PUC, they will be implemented, which is scheduled to happen prior to the opening of the West Rail Line.
Public meeting dates set for proposed bus routes along the West Rail Line
When a new light rail line opens, it also affects the surrounding bus service. It is important to eliminate duplicate service to the rail line while still preserving options for our customers. The draft plans for bus route changes that will take affect when the West Rail Line opens have been developed and will be presented at a series of public meetings. For more information on public hearing dates visit the West Rail website.
Construction Update – Area 1 (Jeffco Government Center to Federal Center?
Current and Ongoing Activities
• Bike path work, including final fabrication, paving and railing installation continues at the Jefferson County Golden Station-Government Center.
• Drainage work and road reconstruction along Ulysses Street could begin later this week, requiring the closure of Ulysses Street between 6th Avenue and Mt. Vernon Road. Crews could be in the area for up to four weeks.
• West Rail crews continue work on Union Boulevard and the on and off ramps of 6th Avenue. Lane closures on the ramps and along 6th Avenue may be in place during daytime hours.
• Work along the frontage road near Red Rocks Station will continue through the month of April.
• Final irrigation and landscape work continues in Area 1.
You can view some photographs of the building process of both the Golden-Government Center parking garage and station on the RTD FasTracks, West Rail Line website.
Information contained in this post adapted from the FasTracks newsletter. To subscribe to the newsletter or get the latest information, see the FasTracks West Corridor website.
Posted by: Julie | Category: Roads & Transportation